Commissioning Checklist

ASI PDQ LaserWash 360+ 100% Commissioning Checklist

Site Information

Pump Stand

  • Pump stand is properly leveled (catch tray under manifold drains properly)
  • Rotation checked on HP pump
  • Rotation checked on LP pump
  • HP pump pressure set to 1000 PSI
  • LP pump pressure set to 200 PSI while operating fluid 1
  • Water saver (HP washdown gun) set to 600 PSI
  • Stand wiped down and metal shavings removed from electrical enclosure
  • Wiring is neat and tidy
  • HP washdown timing set correctly and working properly
  • Re-torqued all hose clamps and verified no leaks after test washes
  • Start up date & store number written inside door
  • All cable grips are tightened properly
  • Remote holder mounted to pump stand with remote
  • Re-torqued all high voltage feeds and terminals (HPP, LPP & transformer)
  • Check HP hoses for crossovers/rubbing

Bay Box

  • 2 shearbolts left inside of bay box
  • Maintenance port installed
  • Ethernet cables labeled
  • Start up date & store number written in enclosure
  • Box is cleaned of metal shavings & all channels installed
  • Wiring is neat and tidy
  • Bay & outside temp sensors installed

E-Chain

  • 2X E-chain support rollers installed
  • Hose clamps re-torqued and verified no leaks
  • All hoses are properly zip tied & secured on both ends
  • Bulkhead bolts properly fastened
  • Grounding straps installed
  • HP supply hose wrapped & not wearing on LP hoses

Bridge

  • Checked nozzle orientation, all nozzles are clear
  • Spray arch tension properly torqued - arch should fall to resting position after impact
  • Back up ultra-sonics adjusted to 12 inches off center line
  • Analog prox sensor set properly (2020 Model) (Config 6)
  • Machine travels to maximum extents without impact
  • Front and rear covers are closed and fastened
  • While performing test washes spray arch maintains proper distance from vehicle - 16"
  • Spray arch clearance above 7FT min
  • Shear-bolt tightened to 20FT-LBS
  • Truck bolts tight
  • 3X foamer media changed to scotchbrite pad
  • Machine & trolly wiped/cleaned
  • Raised ASI sticker on machine bridge cover
  • Cord grips on electrical cabinet tightened
  • Lock down air regulators
  • Check bridge belt tension
  • Gap all 4 directional proxes
  • Check arch impact sensor and verify arch returns to home

Signs

  • Entrance sign properly displaying X & arrow
  • All sign channels on bay sign working properly
  • Speaker working properly on bay sign
  • All sign channels on confirmation sign working properly
  • CDT sign set for correct time & working properly

Blowers

  • Blowers rotation checked
  • Maximum run time set and tested
  • Early shut-down tested
  • CDT matches blower timing
  • Check blowers clearance over 7 FT
  • Raised ASI sticker installed on bridge cover

Underbody

  • Nozzle orientation correct and nozzles clear
  • Anchors cut
  • HP hoses securely fastened and not chafing
  • Start/stop timing adjusted properly for bay

RO Unit

  • RO unit pre-filter replaced
  • RO unit working properly and producing more reject than RO (1.5-1)
  • Verified no leaks
  • Check TDS

RO Tank

  • Valve open and verified no leaks
  • Fill float set at high level
  • Low level float installed and will intercept machine

Offboard Tank

  • Valve open and verified no leaks
  • Fill float set at mid level
  • Low level float installed and will intercept pump

Car Wash Doors

  • Entrance door able to be opened/closed from remote
  • Exit door able to be opened/closed from remote
  • PDQ enter door eyes working properly and reading at 3 or higher
  • PDQ exit door eyes working properly and reading at 3 or higher
  • Weather stripping installed

Entry System

  • Breaker labeled
  • Operating schedule set to match store hours
  • Decals are correct
  • Code wash vended from each package
  • App tested
  • RFID tested
  • Credit tested
  • Stacked wash tested
  • Pushing in E-stop disables entry system
  • Correct coin dispenser wheel installed & configured

Programming

  • Maintenance alerts loaded
  • Users loaded
  • Installed options set correctly
  • Door settings set correctly & temperature control enabled (50> shuts doors)
  • Bay configuration set (config 12)
  • Side sonics offsets loaded
  • Arch buffer set appropriately (between 400-450)
  • Maximum login time set (in advanced user settings)
  • 3X foam disabled over open beds (in dryer settings)
  • Site info & installed date entered
  • Network set correctly and machine able to be remotely monitored
  • Abort & recovery settings set (maximum impacts 2)

Ancillary

  • Air compressor auto drain installed
  • Clearance bar installed at proper height
  • Vacuum tested (if applicable)

Testing

  • Minimum 18 test washes completed
  • Real world test with code until no issues of #1 wash
  • Real world test with code until no issues of #2 wash
  • Real world test with code until no issues of #3 wash
  • Real world test with code until no issues of #4 wash
  • Real world test with code until no issues of #5 wash

Pictures Uploaded to Monday App

  • Bay entrance (outside with entry system)
  • Bay entrance (inbay perspective)
  • Clearance Structure
  • Blowers
  • Bay exit view
  • Vacuums
  • Compressor
  • Pump stand
  • RO Unit

Follow Up — Must Be Communicated With Lead Installer

Final Sign-Off